Building BOM's in DemandCaster

Prior to creating the new BOM, please ensure all the items related to the BOM are already in DemandCaster.

Once ready, go to Data > Data Maintenance > BOM and click "Add New" to get started

For each component of the BOM you are building, enter the following information:

  1. Location where the BOM will be applied (if DRP is enabled on your account)
  2. Child Code: The component within the BOM
  3. Quantity: The quantity of the child (component or sub-assy) needed to build one parent (finished good or sub-assembly)
  4. Click "Save" and continue from step 1 until the entire BOM is complete

Once complete, the completed BOM will appears as follows.

Manually created BOM's may be deleted in the BOM Data Maintenance. Uploaded BOM's may not.

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request